A phased plan to establish Mag 7 immediately, build the complete public-facing website, expand the underlying Base44 platform, strengthen search visibility and transition Porter Homes correctly.
Phase 1
Immediate Launch
12 hrs
Phase 2
Core Website
50 hrs
Phase 3
Platform & Search
38 hrs
Phase 4
Launch & Transition
30 hrs
130
Total Hours
4
Project Phases
10–12
Approx. Weeks
Immediate
Landing Page Launch
Executive Summary
The existing Porter Homes Base44 application will be cloned and used as the technical foundation for Mag 7 Development Group.
This allows the project to retain and reuse the current infrastructure, media library, galleries, uploaded assets and foundational CMS functionality. It avoids rebuilding or rebilling completed work and allows the engagement to concentrate on the Mag 7 rebrand, complete website experience, content architecture, lead generation, technical hardening and long-term growth platform.
The immediate objective is to establish a professional Mag 7 destination for the new domain, QR codes, signage and active marketing.
That same environment will then be expanded into the complete website and supporting digital platform.
Stand up a professional Mag 7 destination within days so marketing, QR codes and signage all point somewhere real.
Carry over the Porter Homes media library, galleries and CMS foundation rather than rebuilding completed work.
Expand the platform into a scalable website, lead-management layer and hardened technical foundation.
Layer SEO, structured data and AEO/GEO content architecture so Mag 7 is found by the right buyers.
Roadmap at a Glance
Immediate Mag 7 Launch
Days 1–4
OutcomeA conversion-ready Mag 7 landing page connected to the selected domain.
Core Website & Brand Experience
Weeks 1–6
OutcomeThe complete public-facing Mag 7 website and primary content experience.
Platform, CMS, Leads & Search
Weeks 4–9
OutcomeA scalable backend, lead-management layer, search foundation and hardened technical platform.
Migration, Launch & Stabilization
Weeks 9–12
OutcomeThe Porter Homes transition, full launch certification, training and post-launch support.
Absolute Urgency · 12 Hours
Days 1–4 after receiving the required assets
12 hrs
Establish a professional, conversion-ready Mag 7 destination that can immediately support QR codes, signage, golf-event materials, direct outreach and active marketing. This is not a disposable temporary page. It will become the foundation of the permanent Mag 7 homepage.
Phase 2 · 50 Hours
Weeks 1–6
50 hrs
Transform the Phase 1 foundation into the complete public-facing Mag 7 website using the supplied consultant brief, existing Porter Homes content and newly provided Mag 7 assets.
About framing
Use framing that presents the business accurately. Avoid labels that make the company appear smaller than it is.
The Mag 7 website presents communities from a development, construction, availability and sales perspective.
Soaring Eagle HOA site covers
The separate Soaring Eagle HOA website should remain focused on resident and homeowner functions. The websites may cross-link where useful, but they have different purposes.
Included
Not included this phase
Phase 3 · 38 Hours
Weeks 4–9
38 hrs
Expand the foundational Base44 CMS already built for Porter Homes into a scalable Mag 7 administration and lead-management platform. This is an expansion of the existing CMS, not a build from scratch.
AEO and GEO complement SEO rather than replacing it.
Included
Requires separate confirmation
Items outside the included set require separate technical confirmation.
Phase 4 · 30 Hours
Weeks 9–12
30 hrs
Complete the Porter Homes transition, certify the Mag 7 platform against the technical launch checklist, train the team and support the initial operating period.
Domain sequence
Phase 1 connects the selected Mag 7 domain to the new landing page.
Phase 4 handles the complete Porter Homes URL migration and supporting-domain strategy.
Project Governance
The 130-hour allowance includes the collaboration and project management needed to keep the engagement transparent and on track.
Project Cadence
Scope Alignment
Items marked Recommendation are our strategic recommendations, not direct brief requirements.
| Brief Requirement → Delivery Phase | Type |
|---|---|
| Brand and positioning | Phase 1 & 2Brief |
| Domain connection | Phase 1Brief |
| Supporting-domain strategy | Phase 4Brief |
| Global navigation and CTAs | Phase 2Brief |
| Home | Phase 2Brief |
| Custom Homes | Phase 2Brief |
| Commercial Construction | Phase 2Brief |
| Land Development | Phase 2Brief |
| Community child pages | Phase 2Brief |
| About and Leadership | Phase 2Brief |
| Contact and booking | Phase 1 & 2Brief |
| Galleries and captions | Phase 2 & 3Brief |
| Home Care Program | Phase 2 & 3Brief |
| Existing CMS expansion | Phase 3Brief |
| Blog-ready architecture | Phase 3Brief |
| CRM and lead workflow | Phase 3Recommendation |
| SEO and metadata | Phase 3 & 4Brief |
| AEO and GEO | Phase 3Recommendation |
| Security and performance | Phase 3 & 4Brief |
| Analytics | Phase 1, 3 & 4Brief |
| Redirect mapping | Phase 4Brief |
| Index cleanup | Phase 4Brief |
| Training and handoff | Phase 4Brief |
| Strategy and project management | Phase AllBrief |
Brand and positioning
Domain connection
Supporting-domain strategy
Global navigation and CTAs
Home
Custom Homes
Commercial Construction
Land Development
Community child pages
About and Leadership
Contact and booking
Galleries and captions
Home Care Program
Existing CMS expansion
Blog-ready architecture
CRM and lead workflow
SEO and metadata
AEO and GEO
Security and performance
Analytics
Redirect mapping
Index cleanup
Training and handoff
Strategy and project management
Important Scope Boundaries
The project assumes timely asset delivery.
Feedback should be consolidated through the approved review group.
Professional photography and drone production are not included.
Paid advertising and paid-media management are not included.
Third-party subscription fees are not included.
A CMS-managed or downloadable lot map is included.
Live GIS or MLS synchronization is not automatically included.
A lightweight lead-management system is included.
Enterprise CRM migration is not automatically included.
One straightforward external integration is included.
Complex integrations require separate confirmation.
Home Care Program website content is included.
Home Care operational software is not included.
Work beyond the approved 130 hours requires additional approval.
Immediate Kickoff Checklist
Check off, confirm, or add notes against each item as it is delivered.
Logo package
Brand palette
Hero imagery
Golf-event or QR-code requirements
Primary-domain confirmation
DNS contact or access
Phone number
Email address
Office information
Lead-notification recipients
Calendly details
Primary conversion goal
Immediate download requirements
Leadership roster
Named approval contacts
Expected feedback turnaround